THIS IS A SCHEDULED EVENT Jan 23 , 21:00 UTC - Jan 31 , 21:00 UTC
Jan 18 , 12:23 UTC
Scheduled - We will shortly begin the migration of our FI-HEL2 data centre to a Telia's flagship data centre in the Nordics. After the migration, we will have improved our redundancy even further in terms of electricity, physical security and connectivity, thanks to having FI-HEL1 and FI-HEL2 in completely separate data centres once again.
The migration will begin on Wednesday, January 23 2019, with expected completion on January 31, 2019. During the migration, your cloud server may lose network connectivity for a brief moment but not more than 5 minutes. No actions are necessary on your part, and all migrations will be carried out outside of business hours (after 9 PM UTC) whenever possible.
As the schedule is rolling, we cannot estimate when a specific cloud server will be migrated or when the migration is entirely completed, but we will update this status page whenever we have any news to share. But please feel free to contact our 24/7 support should you have any questions or need of assistance.
Asiakaspalvelu